Commencement of Schleifmühlchen Roundabout's final reconstruction phase on Monday, entailing asphalt jobs.

Completion of construction for newly built circular mills underway
Completion of construction for newly built circular mills underway

Completion stage for recently built circular mill structures

Construction Update: Final Phase Begins at Schleifmühle Roundabout and Fludersbach in Siegen

The city of Siegen has announced that the final phase of construction work at the Schleifmühle roundabout and Fludersbach is set to begin next week.

Starting Monday, the last asphalt work will take place in the area of the roundabout and the Fludersbach. This work is expected to last for approximately three days, with the entrance area to the Fludersbach being closed during this period. The city has not specified the exact dates for the closure.

During this time, traffic will be detoured to avoid the construction zones. For those coming from Kaan-Marienborn and heading towards Fludersbach, the detour will be via the new bypass at the VEB building towards Lindenberg. In the opposite direction, the detour will be via the temporarily opened Frankfurter Street over Lindenberg and the Wetzlarer Street.

Traffic heading through the Schleifmühle roundabout is being rerouted via the areas surrounding the roundabout to bypass the work zone. For Fludersbach, drivers are guided onto parallel roads that run alongside the construction area to maintain smooth flow. Signage is placed in advance to inform drivers about the detour paths, including clear directions to nearby major roads and residential areas. Public transport routes may also be adjusted temporarily to accommodate the changes in traffic flow.

After these asphalt works, only minor works remain. The city expects to meet the planned opening date for the roundabout at the end of September. It's worth noting that the city has not provided any details about the nature or extent of the minor works that will follow the asphalt works, nor has it mentioned any compensation or alternative arrangements for those who may be affected by the closure of the entrance area to the Fludersbach.

The city has not provided any information about potential impacts on traffic in the area other than the specified detours. However, the detour plan aims to minimize congestion and ensure safety during the final construction phase. For the most detailed and up-to-date information, local traffic authorities in Siegen usually provide specific maps and notices.

The city has not mentioned any changes to the planned opening date for the roundabout, which is expected to be at the end of September. Construction work at the Schleifmühle roundabout in Siegen is in the final phase, marking the end of a significant infrastructure project for the city.

  1. In light of the final phase of construction, transportation alternatives might be necessary for those in the Siegen area, as public transport routes could be temporarily adjusted to accommodate changes in traffic flow due to asphalt works and detours.
  2. With the final phase of construction imminent in the Schleifmühle roundabout and Fludersbach, future developments in the transportation, industry, and finance sectors could benefit from the improved infrastructure and smoother traffic flow once the project is successfully completed.